Video and photographs showing installation of the Mielnik kindergarten modules

Construction of the Communal Kindergarten in Mielnik is under way. In mid April, Climatic delivered 14 modules to the construction site, executing installation works on a regular basis.

The total installation works time – 24 hours over 5 days

The module installation phase was commenced on April 9th and it took only 5 days. The installation works on the construction site took only 24 hours. Thanks to the use of prefabrication, it was possible to prepare the construction site with foundations along with the production of the kindergarten building proper. Finishing works are being performed at the moment. See how did the installation works and transport and its preparation look.

A timelapse video from the construction site