Police station in Pysznica
Design and Construction of a Police Station in Pysznica
The scope of work for the investment included:
- Execution of design works
- Execution of multi-discipline construction works
- Construction of a 10 m high mast
- Delivery and assembly of prefabricated buildings and shelters, land development
- Obtaining the final occupancy permit for the aforementioned facilities on behalf of the contracting authority
- As-built documentation including geodetic inventory
The single-storey Post Office building has:
- A public area and a staff area - each area with a separate entrance
- In the public part: a waiting room, a room for the Duty Office with an application window, an office for 2 people, a toilet adapted for disabled people
- In the office-administrative part: two offices (for 2 and 3 people), manager's room, server room, social part (social room, cloakroom, sanitary unit, drying room)
In addition, as part of the investment:
- Garage and utility building and waste shed
- Cubic capacity of the Post Office building: 608,80 m3
- Cubic capacity of the garage and utility building: 188,50 m3
- Cubic capacity of the waste shed: 23,00 m3
Building parameters:
- Total area of the building - 160 m2
- Prefabrication - 3 modules
- Implementation time - 11 months (4 months ahead of schedule)
- Investment value - 4.8 million PLN
We used some of the photos from the website: https://podkarpacka.policja.gov.pl/rze/aktualnosci/121066,Otwarcie-nowej-siedziby-Postunku-Policji-w-Pysznica.html